Below are lists of construction projects planned and scheduled by the Township for the 2019 season.  

To view current and upcoming road closures and delays, visit https://www.algonquinhighlands.ca/residents/road-closures---delays.php.

Dorset Area

A slurry seal surface treatment will be applied to the following roads to help extend the life of the road surface:

  • Camp Dorset Road
  • Harvey Ave East
  • Russel Landing Road

Stanhope Area

A slurry seal surface treatment will be applied to the following roads to help extend the life cycle of the road surface:

  • Airport Road
  • Barry Line Road
  • Green Lake (Only to the Township boundary)
  • Old Mill Road

The complete road reconstruction project will be taking place on the Walkers Line Road. This project will start Wednesday, May 15 and continue to October 1, 2019, the scope of work will consist of the following;

  • Ditching and shouldering
  • Culvert replacement / resetting
  • Road surface pulverization
  • Gravel application/road grading
  • Double surface treatment

In collaboration with the County of Haliburton, there is a large culvert on Halls Lake West between 1151 and 1163 is scheduled to be replaced. The scope of work will consist of the following;

  • Culvert replacement
  • Bank stabilization
  • Road realignment
  • Road resurfacing over the culvert

During the culvert replacement residents from 1015 to 1157 Halls, Lake Road will be required to enter and exit Halls Lake Road from Highway 35. Residents from 1163 to 1189 Hall Lakes Road will be required to enter and exit Halls Lake Road from Cadge road.

Please expect delays and be cautious when driving through construction zones.

Contact Information

Adam Thorn                                                                          
Operations Manager
Phone: 705-489-2379
E-mail: athorn@algonquinhighlands.ca

Stanhope Public Works Yard
1095 North Shore Road
Phone:  705-489-2600

Dorset Public Works Yard
1850 Kawagama Lake Road
Phone:  705-766-2912